Piping construction, Plant engineering, and Skids and package units
Our services include plant engineering, piping construction, skids and package units for production plants in the pharmaceutical and life science sectors in Switzerland.
Piping for clean and black utilities
Insulation
Fire protection technology
Non-destructive testing
Welding technology
Project management, scheduling, cost and progress reporting.
Skids and package units
Time to market is a decisive factor for the life science industry. The time frame for fabrication can be significantly shortened due to performance of 100% of fabrication-activities in the workshop.
- Downstream and upstream processes
- CIP/SIP systems
- Storage and distribution systems with ozonisation
- Storage and distribution systems for WFI with cooling and heating elements
- Ultrafiltration plants
- Decontamination systems
A FAT (Factory Acceptance Test) on assembled units is performed in the workshop prior delivery. Consequently, the amount of activities on site is reduced to a minimum. Additionally, during commissioning and validation the amount of appearing queries is minor as a check is performed already in advance. Skids from AZI are therefore the solution when time is critical.
AZI plans and builds on the basis of years of experience and comprehensive process know-how, including customised control and visualisation.
Piping and Construction
Our core competence is the mechanical installation of piping for Clean- and Black-Utilities for project in the pharmaceutical industry.
- Safety management
- Prefabrication, installation and system handover for piping and corresponding supports
- Material procurement, incoming inspection and storage
- Quality management, documentation and NDT
- Project management - processing, reporting and scheduling
The demands of projects and the associated decreasing shorter time frames between planning, procurement, installation and system handover require proper planning and quick implementation to changes.
On AZI-projects are working competent and dynamic teams, both in project engineering and also on the construction site. These are experienced with working under this conditions and have already implemented this in various projects for well-known customers in the pharmaceutical and life science sectors.
Projects
Since 2016, we have been jointly implementing projects for life science, pharmaceutical and biotechnology companies in Switzerland. Our services include plant engineering, pipeline construction, skids and package units.
0
Commonyears
> 0 m
Jointlylaid pipes
> 0 h
JointWorking hours
Confidential project
Period: 2016 - 2019, Solothurn, CH, Budget: CHF 55 million
New installation of a biopharmaceutical production plant Sectional piping (clean piping)
- Project and assembly management
- Material procurement (piping, instruments, special parts)
- Prefabrication and installation of 18,000 m of piping incl. primary and secondary supports
- Platforms and insulation
- QA/QC (100% NDT for sterile piping systems)
- Installation of the supplied EMR components
- Passivation
- Documentation
RCF LENGNAU
Period: 2017 - 2020, Lengau, CH, Budget: CHF 60 million
Supply / installation of piping, instrumentation and equipment for the new RCF production plant.
- Manufacturing of pipelines, skids and platforms
- Material procurement and delivery for piping, equipment, machinery and instruments
- Assembly of pipelines, brackets and platforms
Prefabrication and assembly of 3 km piping systems made of carbon steel and stainless steel
- 3,000 m piping incl. instruments and special parts
- Supports
- Insulation
- Documentation
PEREGRINE project
Period: 2019 - 2020, Client: Visp (CH), Budget: CHF 19.7 million
Pipeline construction for 3 production units for Moderna's mRNA vaccine in the IBEX - Building MC1
- 10,000 m piping incl. instruments and special parts
- Brackets
- Insulation
- Documentation
Project VACA White and Black
Period: 2019 - 2020, Client: Visp (CH), Budget: CHF 52.3 million
Prefabrication, assembly and installation of 7 km of carbon steel and stainless steel piping systems
- 7,000 m piping incl. instruments and special parts
- Brackets
- Insulation
- Documentation
Project NSYNC
Period: 2019 - 2020, Client: Visp (CH), Budget: CHF 52.3 million
Detail engineering, prefabrication and assembly of 24 km of carbon steel and stainless steel piping systems
- 24,000 m piping incl. instruments and special parts
- Brackets
- Insulation
- Documentation